 STEEL DELIVERY
We operate on a just-in-time basis and use a supply chain system to make this work.
The steelwork is broken down into erection stages of 20 tons each. The first steel delivered to the works will be the first 20 tons of steel to be erected.
Deliveries are made not only by the day but by the hour. Within 4 hours of delivery, the steel is being processed and raw steel will be converted into painted steel ready for erection within 72 hours of delivery.
|